Standardized Turnkey Project Process
From Technical Consultation To Qualified Product Delivery · One-Stop Complete Solution
Home » Standardized Turnkey Project Process
Phase 1

Project Consultation & Feasibility Study

Duration: 1-2 months

Phase Objective

Determine project feasibility, clarify technical solutions and investment budget.

Phase Deliverables

• Project Feasibility Study Report
• Preliminary Technical Solution
• Investment Estimation Document

Customer Needs Communication

• PUnderstand customer's product needs, capacity requirements, and raw material situation.
• Determine project location, investment budget, and timeline requirements.

Market Research

• Analyze target market demand and competitive landscape.
• Evaluate product pricing and profit margins.
 
 

Technical Solution Development

• Determine process flow and equipment configuration.
• Develop preliminary layout drawings.
 
 

Investment Estimation

• Equipment investment, civil works investment, installation investment.
• Operating costs, economic benefit analysis.

Feasibility Report

• Prepare project feasibility study report.
• Submit to customer for approval.
Phase 2

Engineering Design & Equipment Manufacturing

Duration: 3-6 months

Phase Objective

Complete detailed engineering design, manufacture and procure all equipment.

Phase Deliverables

• Complete Set of Engineering Design Drawings.
• Equipment Manufacturing Completion Report.
• Equipment Inspection Report.
• Equipment Shipping List.

Detailed Engineering Design

• Process Flow Diagrams (PFD).
• Piping & Instrumentation Diagrams (P&ID).
• Equipment Layout Drawings.
• Civil Construction Drawings.
• Electrical Control Diagrams.

Equipment Manufacturing

• Core equipment (sulfonation reactors, etc.) manufacturing.
• Supporting equipment procurement.
• Control system integration.
 
 

Equipment Inspection

• Pressure testing.
• Performance testing.
• Factory acceptance testing.

Packaging & Transportation

• Professional packaging.
• Sea/land transport to project site.
 
Phase 3

On-Site Installation & Commissioning

Duration: 2-4 months

Phase Objective

Complete equipment installation and system commissioning.

Phase Deliverables

• Installation Completion Report.
• Commissioning Report.
• Trial Operation Plan.

Site Preparation

• Inspect civil works completion.
• Confirm utility engineering support.
 
 

Equipment Installation

• Equipment positioning.
• Piping connection.
• Electrical wiring.
• Instrument installation.

System Commissioning

• Single-unit commissioning.
• Linked commissioning.
• System commissioning.
• Control system commissioning.

Trial Operation Preparation

• Prepare raw materials and auxiliary materials.
• Train operators.
• Develop trial operation plan.
 
Phase 4

Trial Operation & Performance Verification

Duration: 1-2 months

Phase Objective

Verify unit performance and produce qualified products.

Phase Deliverables

• Trial Operation Report.
• Performance Verification Report.
• Product Quality Testing Report.

Feed Trial Operation

• Gradual feed, adjust process parameters.
• Resolve issues during trial operation.

Performance Optimization

• Optimize reaction temperature, pressure, ratio, and other parameters.
• Improve product quality and capacity.

Performance Verification

• Continuous operation for over 72 hours.
• Verify capacity, quality, energy consumption, and other indicators.
• Prepare performance verification report.

Product Testing

• Commission third-party testing agency to test product quality.
• Ensure products meet national standards.
 
Phase 5

Personnel Training & Documentation Handover

Duration: 0.5-1 month

Phase Objective

Train customer personnel and hand over technical documentation.

Phase Deliverables

• Training Records and Assessment Reports.
• Complete Set of Technical Documentation.
• Spare Parts List and Supply Channels.

Operation Training

• Equipment operation training.
• Process control training.
• DCS system operation training.

Safety Training

• Safety operation procedure training.
• Emergency handling training.
• Fire safety knowledge training.

Maintenance Training

• Equipment routine maintenance training.
• Fault diagnosis and troubleshooting training.
• Spare parts replacement training.
 

Documentation Handover

• Equipment operation manuals.
• Process technical manuals.
• Equipment drawings and documentation.
• Spare parts list.
Phase 6

After-Sales Service & Continuous Support

Duration: Long-Term

Phase Objective

Provide long-term technical support to ensure stable unit operation.

Phase Deliverables

• After-Sales Service Agreement.
• Regular Follow-up Visit Reports.
• Technical Optimization Recommendations.

Warranty Period Service

• Free repair and replacement during warranty period.
• Regular follow-up visits to resolve operational issues.

Technical Support

• 7×24-hour technical consultation.
• Remote diagnosis and guidance.
• Emergency on-site service.
 

Spare Parts Supply

• Long-term supply of original spare parts.
• Ensure spare parts quality and supply cycle.
 
 

Process Optimization

• Optimize processes based on operational conditions.
• Provide technical upgrade services.

Capacity Expansion & Retrofit

• Provide capacity expansion services.
• Technical transformation and upgrades.
WE ARE HERE TO HELP YOU
Qino is a full-service provider , delivering end-to-end solutions from project planning to commissioning.

 WhatsApp: +8613338813031
 Email: njqino@gmail.com 
 Add: Building 28, Botong Innovation Industrial Park, No. 2 Qiancheng Road, Liuhe District, Nanjing, Jiangsu Province, China

Quick Links

Product Category

Other Links

Leave a Message
Contact Us

Copyright© 2026 Nanjing Qino Automatic Control Equipment Co., Ltd.All Rights Reserved.|苏ICP备2023026141号-1